Categories: /01 Feb 2012

Palm Beach County Environmental Resource Management (ERM)

Lake Worth, FL

Engineer of Record
Bridge Design Associates, Inc.

Date of Completion
February 2012

Contract Bond

Demolition of Old Lake Ave Concrete Bridge (West Side). Installation of (+/-) 200 – 14” concrete pile (Fishing Pier/Boardwalk/Kayak) and 9 -18” concrete pile (Floating Dock). New Seawall consisting of the installation of 200lf composite sheeting and concrete cap with rip rap boulders placed at the toe. Construction of; A. 600’ x 8’ wood fishing pier and B. 600’ x 6’ boardwalk pier with Observation Platform, including Metal Roof. Installation of an 8 slip floating dock and kayak launch. Upland improvements including; new concrete sidewalks, asphalt and stripping, pedestrian benches and bike racks.